Anwick drivers: A153 resurfacing still on track for September
As of 5 August 2026, the A153 works in Anwick are still on course for an early September completion, with Lincolnshire County Council confirming the programme has not slipped. The latest update says crews have moved from the west side of the village into the next construction phase east of Anwick, so the schedule remains live for residents, school transport operators and local businesses.
Current project status on the road
Since works started around three weeks ago, the team has laid more than 3,500 tonnes of road-building material and finished resurfacing on the western section. The project manager’s update says a sustained dry spell has helped work progress as planned despite heat, which reduced the risk of delays from weather-related setbacks. The project is designed to rebuild the carriageway and drainage together, not just apply a temporary surface.

What has shifted since earlier progress checks
Council sources confirm the active focus is now on the east side of Anwick, where excavation and reconstruction are under way. In total, around 6,000 tonnes of new road material are expected across the full scheme, so the remaining work is the larger structural stage rather than just finishing touches. The wider Strategic Route Surfacing programme behind this is a £12 million maintenance plan, with additional routes such as the A15, A151, A57, A1031, A606 and B1174 also scheduled in 2026/27.

Timeline and disruption plan
| Milestone | Status |
|---|---|
| Latest confirmed update | 5 Aug 2026 |
| West of Anwick | More than 3,500 tonnes used and section resurfaced |
| East of Anwick | Excavation and reconstruction now underway |
| Overall material use | Around 6,000 tonnes in total for this scheme |
| Works window | Weekday evenings overnight |
| Completion target | Early September |
What this means for motorists and residents
Cllr David East said the scheme is about protecting a key county route, not only creating one smoother stretch. For daily users, the practical effect is reduced pothole risk and fewer future emergency repairs if the rebuild is completed on time. The council is also improving verge drainage at the same time, which is intended to extend carriageway life and limit repeated water-related damage. The next confirmed milestone is completion of the east-side reconstruction before the early September handover phase.
Source: Lincolnshire County Council
Context & actions About this article
Source check Local source trail
Used the council release wording and figures directly, with emphasis on confirmed dates, quantities, and work phases.
- Checked that the project is described as on track with an early September target in the 5...
- Confirmed two key material figures from the release: 3,500+ tonnes already used west of An...
- Checked that reported disruption is managed mainly through weekday evening and overnight w...
- Confirmed the quoted programme context: A153 is part of the council's £12 million Strategi...
- Source
- Lincolnshire County Council
- Scope
- Anwick, Lincolnshire, UK
- Updated
- 2026-08-05 10:19
Source check
Report a trust issue
Send a clear signal to community moderation if the source, facts or context need review.
Comments